Denmark's Energimærkning scheme uses Be18 to assess commercial buildings. On-site renewable generation from wind turbines and solar is credited in the calculation — but is capped at 25 kWh/m²/year combined. MEPS is coming, with specific threshold levels pending secondary legislation.
Of the five countries covered on this site, Denmark is the only one with a statutory cap on on-site renewable generation credit in the energy assessment. Be18 caps the combined credit from wind turbines and solar cells at 25 kWh/m²/year reduction in primary energy need. This is a hard ceiling, not a proportional limit. Generation above this threshold delivers no additional benefit in the energimærke calculation.
This is confirmed from the CA-EPBD Denmark 2020 primary report and is material for any building owner or practitioner working with on-site generation in Denmark.
Lovbekendtgørelse 1253/2025, Energistyrelsen, the A2020/A2015/A2010 scale, certified firm requirement.
Scheme in force since 2006, infringement proceedings opened July 2026, MEPS pending — 2027/2030/2033 targets.
Criminal bøde (fine) with building size aggravation; Energistyrelsen administrative fines; compliance order mechanism.
Be18 monthly calculation, 25 kWh/m²/year on-site generation cap (wind + solar combined) — stated explicitly.
Understanding what this means for your building → Owner pathway
Every claim on this page is sourced. Sources and verification dates are on each sub-page. Verified: 25 Aug 2026.