RESS is Ireland's grid-scale renewable electricity auction scheme — not a grant for individual buildings. For on-site generation at commercial premises, the routes are the SEAI NDMG solar grant, SEAI EXEED capital works grant, and the Clean Export Guarantee for export revenue.

What RESS is — and who it is for

The Renewable Electricity Support Scheme (RESS) is the Irish government's main support mechanism for grid-scale onshore and offshore renewable electricity generation. It operates through competitive auctions where renewable electricity developers bid for a 15-year Contract for Difference (CfD) support arrangement. EirGrid administers the auctions.

RESS is not a grant scheme for individual commercial buildings. A building owner installing an on-site wind turbine or solar PV system for self-consumption does not apply for or receive RESS support. RESS is designed for utility-scale electricity generators exporting to the grid.

RESS 6 is expected in the second half of 2026. Five RESS auctions have been completed. The scheme aligns with Ireland's target of 80% renewable electricity by 2030.

Sources:

SRESS 1 — the small-scale export route for commercial self-consumers

The Small-Scale Renewable Electricity Support Scheme (SRESS 1) was introduced for projects in the 50 kW to 1 MW range that export electricity to the grid. Unlike RESS (which uses a competitive auction), SRESS 1 provides support at centrally set tariff rates — no auction required.

Relevant to: commercial buildings with generation capacity of 50 kW to 1 MW where a proportion of output is exported. A commercial building with a 100 kW wind turbine exporting surplus generation would typically be in scope.

Not relevant to: buildings where generation is primarily for self-consumption with minimal export, or installations below 50 kW — those use the Clean Export Guarantee (CEG) under the Microgeneration Support Scheme instead.

Source:

The Microgeneration Support Scheme — for installations under 50 kW

For commercial buildings with on-site generation below 50 kW, the Microgeneration Support Scheme and its Clean Export Guarantee (CEG) is the relevant export revenue mechanism.

CEG requires a qualifying generation installation and a smart export meter. The export rate is set commercially by the supplier — a positive rate is required, but there is no government floor above zero. Review the tariff annually; rates can change with approximately 30 days' notice.

For the capital grant on the solar PV component of a combined installation, see SEAI NDMG.

Which scheme applies — decision table

Irish export support — which scheme applies
Grid-scale renewable developer — onshore wind, offshore wind, large solarRESS auction
Commercial building, generation 50 kW–1 MW, exporting to gridSRESS 1
Commercial building, generation under 50 kW, exporting surplusMicrogeneration Support Scheme — CEG
Commercial building — solar PV capital grantSEAI NDMG — up to €162,600 for up to 1,000 kWp
Commercial building — broader energy project capital grantSEAI EXEED
Energy efficiency tax deductionAccelerated Capital Allowance (ACA)
Lower-cost financing for SME energy investmentSBCI Green Transition Finance

BER improvement — the direct link for commercial building owners

RESS and SRESS 1 improve Ireland's national renewable electricity mix, which over time affects the primary energy factor applied to purchased electricity in NEAP/iSBEMie BER calculations. However, this is a national calculation parameter — it is not a building-level credit that the building owner controls.

Building-level BER improvement through on-site generation is credited directly in the NEAP calculation — and crucially, without any cap. Ireland's NEAP/iSBEMie credits the full consumed output of a qualifying on-site generation installation. This contrasts with Denmark, where the combined generation credit is capped at 25 kWh/m²/year.