On-site wind generation is explicitly included in Ireland's NEAP/iSBEMie methodology with no statutory cap. A wind turbine also contributes to the Renewable Energy Ratio required under NZEB rules for new buildings.
On-site wind generation is explicitly credited in Ireland's NEAP (Non-Domestic Energy Assessment Procedure) using iSBEMie v5.7b. A wind turbine reduces the building's net delivered energy requirement — the figure used to calculate the BER class. There is no statutory cap on the credit, unlike Denmark's Be18 framework which limits combined wind and solar credit to 25 kWh/m²/year.
The current version matters here: iSBEMie v5.7b (released 8 July 2026) introduced updated primary energy and CO₂ factors under EPBD 2024 implementation. Earlier versions (v5.5h, v5.6a) used older factors. Any assessment carried out before July 2026 used different energy factor weightings. The direction of change — revised electricity carbon factors reflecting Ireland's increasingly renewable grid — generally benefits on-site generation in the calculation.
For new commercial buildings, wind generation also contributes to the Renewable Energy Ratio (RER) required under TGD Part L 2022 NZEB rules. New non-domestic buildings must meet a minimum RER of 20%. On-site wind generation counts directly toward this threshold.
The NEAP Modelling Guide (Q2 2026) and the iSBEMie v5.7b Technical Manual (June 2026) are the authoritative sources for how wind generation is entered and credited in the assessment. The SEAI NEAP page publishes both documents.
There is no specific NEAP figure for band improvement from wind without a site-specific assessment. The improvement depends on the building's baseline BER, total floor area, and the turbine's modelled annual output.
Source: SEAI NEAP page (primary); NEAP Modelling Guide Q2 2026