Klimatklivet scores applications on CO2 reduction per SEK of grant requested. A combined wind, storage, and EV charging installation produces three CO2 reduction streams in one application — structurally stronger than any single-technology competitor.
Klimatklivet is Sweden's primary grant programme for investments with high climate benefit. Administered by Naturvårdsverket (Swedish Environmental Protection Agency) through county administrative boards (länsstyrelser). Open to municipalities, regions, companies, and organisations — private individuals are excluded.
Eligible technologies include wind generation, battery energy storage systems, EV charging infrastructure, renewable heating, and circular economy measures. Biogas for electricity and heat was removed from scope from autumn 2025.
Source: Naturvårdsverket Klimatklivet. Verified: 1 Sep 2026.
Municipalities, regions, companies, and organisations making qualifying investments with demonstrable CO2 reduction benefit. Private individuals are not eligible.
EV charging for public access: up to 70% of eligible costs. Wind generation and BESS: competitive scoring — no fixed published rate; the grant is calculated on CO2 reduction per SEK of grant requested.
Grant applications are scored on the ratio of CO2 reduction to grant amount requested — SEK per tonne CO2 avoided. There is no fixed rate; the score determines the grant.
A combined installation — wind generation displacing grid electricity, BESS enabling peak shaving and increased self-consumption, EV charging replacing diesel vehicle fuel — produces three separate CO2 reduction streams in a single application. Single-technology applications submit one stream; a combined application submits three. The aggregate CO2/SEK ratio is structurally stronger than any single-technology competitor submitting the same total grant amount.
Autumn 2026 round: 24 August — 4 September 2026. Eleven calendar days.
Missing a round means a six-month wait for the next. Applications must be complete and ready before the window opens — beginning preparation on the opening day is too late. The county administrative board (länsstyrelse) portal for the county where the project is located is the submission route.
Next round timing: typically spring and autumn. Confirm with Naturvårdsverket for the 2027 spring window date.
Klimatklivet (project grant) can combine with ROT tax relief on labour costs. It cannot double-fund the same cost component. An EKL energy audit action plan that names specific measures provides the CO2 calculation basis that strengthens a Klimatklivet application — the relationship is sequential and designed.