The scheme stops issuing certificates to new entrants in 2035. A project registered in 2026 receives certificates until 2041 — six years after the scheme closes. "The scheme ends in 2035" is true for new projects after that date. For a 2026 installation, it is not.
The elcertifikat (electricity certificate) scheme supports qualifying renewable electricity generation in Sweden and Norway under a joint certificate market. Generating installations receive one certificate per MWh of qualifying production. Certificates are sold to obligated electricity suppliers, creating an ongoing revenue stream alongside the electricity itself.
Administered by Energimyndigheten (Swedish Energy Agency).
Source: Energimyndigheten Elcertifikatsystemet. Verified: 1 Sep 2026.
A new project registered in 2026 receives electricity certificates until 2041.
The scheme stops issuing certificates to new registrations from 2035. But existing projects — including any registered in 2026 — continue receiving their full 15-year certificate allocation regardless of the 2035 new-entrant closure date. A 2026 registration runs to 2041.
Building owners told the scheme is effectively over for new projects are working from a misreading of the sunset provision. The headline — "scheme ends 2035" — applies to new entrants after that date, not to installations registered before it.
Qualifying renewable electricity generation installations registered with Energimyndigheten. Eligible technologies include wind, solar, hydro, bioenergy, and wave power. The installation must meet technical and registration requirements confirmed with Energimyndigheten.
Certificate prices are set by the market and fluctuate. They are not a fixed tariff. The revenue per MWh of qualifying generation depends on the prevailing market price at the time of sale.
The certificate revenue is additional to the electricity export or self-consumption value — two separate income streams from the same generating installation.
Registration is through Energimyndigheten's certificate register. New installations must apply before generation begins. Confirm current registration requirements and eligibility criteria with Energimyndigheten directly.