News

Ireland introduced simplified BER scale and new A0 class from May 2026

Ireland moved from a fifteen-band BER scale to a simplified eight-band scale on 24 May 2026. The change was introduced by S.I. No. 168/2026, which also updated the non-domestic assessment tool to NEAP/iSBEMie v5.7b and introduced a new top class — A0 — defined as a zero-emission building.

What changed

The previous scale ran from A1 (best) through A2, A3, B1, B2, B3, C1, C2, C3, D1, D2, E, F, G — fifteen bands. The new scale has eight: A0, A, B, C, D, E, F, G. The old A1/A2/A3 sub-classifications are replaced by a single A band, and A0 sits above as a new top class.

A0 is defined as a zero-emission building with primary energy demand below 42 kWh/m²/year. This is consistent with the zero-emission building definition in the EPBD 2024 recast and aligns Ireland's top class with the equivalent class introduced in Sweden on the same date under SFS 2026:744.

Certificates issued under the old fifteen-band scale are not automatically reissued. They remain valid until expiry. Owners seeking an A0 designation must commission a new assessment under NEAP/iSBEMie v5.7b.

Sources:

The new assessment tool

NEAP/iSBEMie v5.7b was released on 8 July 2026. It incorporates the simplified scale and updates the electricity primary energy factor from the figure used in v5.6a to 1.75. On-site wind generation is credited against the primary energy figure without a statutory cap — unlike Denmark, Ireland places no ceiling on the generation credit in the BER calculation.

Non-domestic BER assessments from 8 July 2026 onwards must use v5.7b. Assessments conducted before that date under earlier tool versions are not required to be redone unless the certificate expires.

MEPS — the confirmed timeline

Ireland's MEPS obligations are derived from the EPBD 2024 recast. The confirmed timeline, pending enactment of the final Irish statutory instrument:

These dates were confirmed in the legal analyses published by William Fry and IBC Ireland following the EPBD recast transposition deadline in May 2026. The Irish SI implementing these obligations in domestic law is expected before the January 2027 compliance date.

The penalty for non-compliance with the existing BER certificate obligation is up to €5,000 per instance, enforced by local Building Control Authorities.

Sources:

→ Full Irish regulatory reference — BER, MEPS deadlines, and NEAP methodology

→ Irish financial incentives — SEAI EXEED, BMS Grant, Accelerated Capital Allowances

Verified: 15 Sep 2026