MEPS for existing commercial buildings in Ireland are pending secondary legislation. Ireland transposed the BER scale element of EPBD 2024 on time — but the full transposition package, including MEPS, was incomplete by the May 2026 EU deadline, triggering infringement proceedings.
Minimum Energy Performance Standards (MEPS) for existing commercial buildings in Ireland are required under EPBD 2024 (Directive 2024/1275, Article 9) but have not yet been enacted in Irish law.
Ireland's position as at August 2026: the BER scale simplification (S.I. 168/2026) was transposed on time in May 2026, making Ireland one of the few early movers on that specific provision. However, the full EPBD 2024 transposition package — including MEPS for existing buildings, renovation passports, and digital building logbooks — was not notified to the European Commission by the 29 May 2026 deadline. The Commission opened infringement proceedings against Ireland (along with all other 26 EU member states) on 15 July 2026. The existing BER obligations under S.I. No. 666 of 2006 remain fully in force — infringement proceedings relate to the incomplete transposition, not to a failure of current obligations.
The EPBD 2024 MEPS timetable requires member states to define thresholds corresponding to the worst-performing 16% of non-residential stock by 2030 and the worst-performing 26% by 2033. For Ireland, these thresholds will be set through secondary legislation by the Department of the Environment, Climate and Communications (DECC) and SEAI. The specific BER class levels that will constitute MEPS in Ireland have not been proposed or consulted on publicly as at August 2026.
The Dublin commercial office market is already applying de facto MEPS pressure through lease negotiation and green finance requirements — buildings below B are experiencing lettability and covenant pressure independent of any regulatory minimum.
Source: European Commission infringement proceedings, 15 July 2026; CA-EPBD Ireland